Site protection with a Building Management System (BMS) for a high court building
Context and challenges
This project concerns the construction of a new High Court building. The building includes a base structure beneath a 40-storey, 160-metre tall tower comprising three stacked blocks, and a second 8-storey building. It includes a 5,500 square metre public lobby, 90 courtrooms and 30,000 square metres of office space. This building is extremely innovative, both in terms of its architecture and its energy-saving comfort management equipment. The goal of the building is to ensure optimised energy consumption and maximum flexibility suited to a building intended to welcome both legal professionals and the general public, with a constantly-changing configuration.
The client, a leader in the construction sector, called on Assystem to integrate the Centralised Technical Management system using next-generation, "Smart Building" technology coupled with industrial IT systems.
Missions
Assystem designed, installed and integrated all the BMS equipment and coordinated "multi-trade" installation of comfort equipment in the offices and meeting rooms:
- Creation of comprehensive development cycle, from specification through to production launch
- 3D modelling of drawings using a BIM tool (REVIT)
- Design, mock-ups and laboratory tests on comfort equipment and room controls
- Modelling of BMS data and interfaces
- Development of operational Human Machine Interfaces (HMI)
- Testing on platforms and on-site commissioning
- Deployment of reporting system for energy consumption
Client Benefits
In order to guarantee maximum flexibility for this type of venue, which is designed to accommodate judges and the public in a constantly changing configuration, Assystem proposed the implementation of an innovative solution allowing the cross and unified management of heating, cooling, lighting and blinds, associated with office occupancy information, and allowing the energy optimisation of this high-rise building (Low Energy Building objective: 70 kWhep/sqm/year).
in figures
-
2,000controllers
-
80concentrators
-
100,000centralised points
CITIES & TERRITORIAL DEVELOPMENT : related projects
Master framework agreement for provision of environmental surveying, monitoring, reporting and related Services
Know moreProject management consultancy for redevelopment of an airport at Republic of Maldives