Mitigating Co-Activity Conflicts and Resource Overallocation in Construction Projects
Khwansiri Ninpan
Technical Solution Lead in the Optimisation Domain
Khwansiri is a versatile professional with a dual degree in Artificial Intelligence and Medical Microbiology. Her experience in healthcare has given her a profound understanding of research processes and the significance of data-driven insights.
With over 4 years of experience as a data scientist at Assystem, Khwansiri has specialised in developing algorithms to optimise project planning under complex constraints. In 2023, she transitioned into a technical solutions lead role in the optimisation domain, leveraging her diverse skill set to solve complex problems, drive innovation, and contribute to research and development initiatives.
Mitigating co-activity conflicts and resource overallocation in construction projects: A modular heuristic scheduling approach with Primavera P6 EPPM integration
Abstract
This paper proposes a heuristic approach for managing complex construction projects.
The tool incorporates Primavera P6 EPPM and Synchro 4D, enabling proactive clash detection and resolution of spatial conflicts during concurrent tasks.
Additionally, it performs resource verification for sufficient allocation before task initiation. This integrated approach facilitates the generation of conflict-free and feasible construction schedules. By adhering to project constraints and seamlessly integrating with existing industry tools, the proposed solution offers a comprehensive and robust approach to construction project management.
This constitutes, to our knowledge, the first dynamic digital twin for the delivery of a complex project.